You plan to answer a few emails before lunch and are still at it at two o’clock. A weekend decorating job stretches into three weekends. A report you expected to write in an evening takes a week.

The short answer to why this keeps happening: when we estimate our own tasks, we picture the plan going smoothly and forget how often things have not. Psychologists call this the planning fallacy, and it affects students, professionals and governments alike.

Where the idea came from

The term was introduced in 1979 by the psychologists Daniel Kahneman and Amos Tversky. They noticed that people making forecasts tend to focus on the specific case in front of them, building a story of how it will unfold, while neglecting a more useful question: how long do tasks like this usually take?

Kahneman later called these two approaches the inside view, which looks at the details of this particular plan, and the outside view, which looks at what usually happens in similar cases.

The thesis study

In 1994, Roger Buehler, Dale Griffin and Michael Ross put the idea to the test with university students writing their final-year theses.

The students predicted, on average, that they would finish in about 34 days. They were also asked how long it would take if everything went as badly as it possibly could: about 49 days on average.

In reality, the students took about 56 days on average. Only around 30% finished by the date they had predicted. Even their worst-case estimates were too optimistic.

Buehler and his colleagues found the same pattern with other tasks, from school assignments to everyday jobs at home. People were well aware that their past projects had often run late. They simply didn’t use that knowledge when predicting the next one.

Why we underestimate time

Several things combine:

  • We plan forwards, step by step. When we imagine a task, we picture the main steps going as intended. Interruptions, delays and problems are hard to imagine in advance, so they aren’t included.
  • We treat each task as unique. It’s easy to think this time is different: the last project overran because of an unusual problem that won’t happen again. But there is almost always some unusual problem.
  • We don’t break tasks down. A task described as a whole, such as “clean the kitchen”, seems shorter than the same task listed in its parts. In 2004, Justin Kruger and Matt Evans found that asking people to unpack a task into its smaller steps led to longer, more realistic predictions.
  • We want it to be quick. Hope and pressure, from ourselves or from others, push estimates towards what we would like to happen.

Not just a personal problem

The same bias shows up in very large projects. The planning researcher Bent Flyvbjerg has studied major infrastructure projects around the world and found that cost overruns and delays are common rather than rare. He argues that planners should use reference class forecasting: base estimates on the actual results of a group of similar past projects, applying Kahneman and Tversky’s outside view on a larger scale.

How to plan more realistically

1. Look back before you look ahead

Before estimating, ask: How long did something similar actually take last time? If you don’t know, start keeping a simple record of how long regular tasks take. Your own history is the best predictor you have.

2. Unpack the task

List the steps, including the small ones: gathering materials, waiting for replies, checking work, tidying up. Estimate each, then add them together. This is the approach Kruger and Evans found reduced underestimation.

3. Add a buffer

If your tasks usually overrun, plan for it. Adding extra time to your first estimate, especially for anything new or involving other people, is not pessimism. It is using evidence.

4. Decide when and where you will do it

In a 2000 study, Sander Koole and Mascha van’t Spijker found that when people made specific plans for when and where they would work on a task, they tended to finish it faster. Concrete plans don’t just make estimates better; they help reality catch up with the estimate. Techniques such as time blocking build this into a schedule.

5. Ask someone who has done it before

A colleague or friend who has done a similar job can tell you how long it actually took them. That is the outside view in its simplest form.

6. Prioritise, because time is limited

When everything takes longer than planned, choosing what matters most becomes even more important. The Eisenhower matrix is a simple way to decide what to do first and what to drop.

Is it the same as procrastination?

No, although they often appear together. Procrastination is putting off a task you intend to do. The planning fallacy is misjudging how long a task will take. Underestimating time can make it easier to delay starting, because the task seems smaller than it is. Our article on why we procrastinate explores that side of the problem.

Frequently asked questions

Why is it called a fallacy?

Because it is a consistent error in reasoning, not just bad luck. People underestimate time even when they know their previous, similar tasks overran.

Does experience help?

Only if we use it. The thesis study showed that people knew their past projects had often run late, but didn’t apply that knowledge to new predictions. Deliberately recalling past results helps.

What is Hofstadter’s law?

A humorous rule coined by the writer Douglas Hofstadter: a task always takes longer than you expect, even when you take that rule into account. It is a playful summary of the planning fallacy.

Sources and further reading

  1. Kahneman, D. and Tversky, A. (1979). Intuitive prediction: biases and corrective procedures. TIMS Studies in Management Science, 12, 313–327.
  2. Buehler, Griffin and Ross: Exploring the “planning fallacy”: why people underestimate their task completion times, Journal of Personality and Social Psychology (1994)
  3. Kruger and Evans: If you don’t want to be late, enumerate: unpacking reduces the planning fallacy, Journal of Experimental Social Psychology (2004)
  4. Koole and van’t Spijker: Overcoming the planning fallacy through willpower: effects of implementation intentions on actual and predicted task-completion times, European Journal of Social Psychology (2000)
  5. Flyvbjerg: From Nobel Prize to project management: getting risks right, Project Management Journal (2006)